Greenwell Springs Road Overlay Update

By  | 

Update from Project Manager Jeffery Chatelain; Submitted by David Barrow

    Our contractor has completed asphalt patching work and the majority of asphalt milling operations. The milled asphalt surface is what you are riding on now and is required prior to placement of the new asphalt.  The cold weather has delayed progress somewhat since we cannot put down new asphalt pavement if the temperature is below 50 degrees. Weather permitting, the contractor plans to begin paving asphalt after the first of the year.