Magnolia Bridge Replacement Project Update

By  | 

Submitted by Rep. Clif Richardson's Office

Crews are currently hauling embankment and driving piles, which act as a support for the bridge. They are also forming and pouring caps to be placed on top of the piles to form bents. These bents will allow crews to place girders, which are currently being casted. To date crews have driven 82 of 180 piles and poured 11 of 30 caps.


ABOVE: East view and the forming of caps for the Magnolia Bridge
 
For questions or comments, contact DOTD’s Customer Service Center at 1-877-4LA-DOTD (1-877-452-3683) or e-mail [email protected]. The center is open 7:30 a.m. – 5 p.m., Monday through Friday. You can also visit the project’s Web page by going to www.dotd.gov and clicking on "Projects" from the Programs & Projects section of the main menu on the left-hand side of the page and selecting the LA 64 Magnolia Bridge Replacement Project link.
You can also follow the La. 64 Magnolia Bridge Replacement Project on Facebook.
Again, we thank you for your feedback and patience during this construction. Additionally, at your convenience, please let us know how we are doing by filling out our Customer Service Survey.
State Project Number: 262-31-0016
Start date: October 2010
Finish date: Fall 2012
Cost: $19.9 Million
Contractor: L & A Contracting Co. of Hattiesburg, MS